Understand the impact before changing the plan.
This page introduces the extended Scenarioverksted demo and provides a step-by-step guide. Open the demo with the button below to edit a complete plan and compare multiple alternatives.

Try it / Fjordverkstedet
What if the delivery is delayed?
The example starts with 480 hours of work, four people, 7.5 hours per day and 80 percent availability. Including preparation and checks, the baseline takes 24 working days.
Open the example project
Select Fjordverkstedet and the Overview tab. This guide uses the original example values. If you have edited the project before, your figures may differ.
Select “Forsinket leveranse”
Five working days of waiting move the result from 24 to 29 working days. See how the waiting time appears on the timeline.
Select “To ekstra personer”
Staffing increases from four to six people while the five waiting days remain. With these assumptions, the model shows 23 working days. Open Comparison to see the alternatives together.
These figures apply to the unmodified example project. Your changes and working calendar affect the result. The cost display covers the model’s resource cost, not a complete project budget.
From an example to your own project.
Enter activities, dependencies, milestones and resource groups. Create alternative plans and explore which assumptions actually change the delivery.
The project can be saved as a file and reopened. Comparisons can be exported as CSV, and the report can be printed or saved as a PDF from the browser.
A tool for exploring assumptions.
This is an extended demo under development. Calculations follow fixed rules and use no LLM or AI service in the background. The result supports discussion and must be checked against actual conditions before use in a real project plan.
Project data is stored in the browser on your device, without automatic syncing between devices. Download the project file as a backup; clearing browser data can also delete the project.
Want a simpler introduction?
The short concept demo introduces the idea with fewer choices. The extended demo lets you work with a complete plan and multiple alternatives.