Simple demo / Scenarioverksted

What happens
when the plan changes?

A delivery is delayed. The team gets more work. Or two extra people can help. Explore the alternatives and see how they affect the schedule.

FjordverkstedetA technical delivery · Fictional example
Local calculation

Try a change.

Beyond target
Total duration29working days in the model
Against baseline+5more working days
Margin to target−4working days beyond target
Daily capacity24productive hours per day

Two paths to completion.

Working days from the start

Day 0Day 30
PreparationWaitingExecutionReviewDashed line: target

What would it take to meet the target?

With these assumptions, at least 5 people would be needed to finish within 25 working days.

Assuming work can be shared equally and capacity increases linearly.

You should be able to
follow the calculation.

This is a simple, verifiable model. Every result follows from the numbers you choose.

See the figures side by side
Baseline and your scenario
MeasureBaselineYour scenario
How the result is calculated
  • Daily capacity = people × 7.5 hours × available share.
  • Execution = work scope / daily capacity, rounded up to whole working days.
  • Total duration = 2 preparation days + waiting + execution + 2 review days.
  • Margin = target − total duration. A negative margin means the target is exceeded.
What the model simplifies

Phases run sequentially. Waiting comes before execution. More people provide proportionally more capacity. The model does not account for onboarding, space constraints, overtime, different skills, public holidays or parallel tasks.

Work scope is measured in productive hours. Days are working days, not calendar dates. This is a fictional example and does not guarantee an actual delivery date.

Calculations run in your browser, with no AI calls or uploads. Your selections carry over when you change language. The example contains no customer data.

One concrete question.
A useful first tool.

A client pilot starts with one decision you actually need to make. We agree the calculation rules with a specialist and check the model against known examples before use.

Which alternatives would you like to compare?

Let’s talk